WP3 demonstration on grid forming: storage system now installed at RTE substation



The two containers integrating the batteries, supercapacitors and inverters, previously tested at INGETEAM  lab, have been delivered and installed at RTE substation Castelet Luzenac.
The first onsite tests will start in September, for an operational launch in early October.